Laying 533 kilometers pipeline for Melamchi project completes

Kathmandu, Feb 18: Of the total 670 kilometers water pipeline to be laid in Kathmandu valley for the Melamchi water project, work on 533 kilometers has been completed, said the Project Implementation Directorate, Kathmandu Upatayaka Khanepani Limited.

The information was shared at a programme organised by the Directorate in the Capital on Friday. Project director of the Directorate Tiresh Prasad Khatri said laying pipeline at various 40 places is ongoing.

On managing dusts emanated from digging road to lay pipeline, he said efforts are on in this regard as per Environment Protection Act and the Safeguard Policy of Asian Development Bank.

प्रतिक्रिया दिनुहोस्
सम्बन्धित वर्गका समाचारहरू

पार्टी विभाजनविरुद्ध उभिन प्रदेश र स्थानीय तहका जनप्रतिनिधिलाई एमालेको निर्देशन

 भदौ १४, काठमाडौं : नेकपा एमालेले दल विभाजनमा सहभागी नहुन प्रदेश र स्थानीय तहका जनप्रतिनिधिलाई

A ‘think tank’ on Nepal law and affairs

A lawyer who took his job seriously, he had deep knowledge of the global geopolitics,

President calls for justice to Nirmala

September 14, 2018 President Bidya Devi Bhandari  KATHMANDU, Sept 14: President Bidya Devi Bhandari has

BIMSTEC leaders say they are committed to enhancing connectivity

Leaders from the seven-nation regional grouping emphasized the importance of exploring multiple avenues of connectivity,

BIMSTEC members should prioritise poverty alleviation: PM Oli

-Kathmandu Aug 30, 2018-Prime Minister KP Sharma Oli has stressed the Bay of Bengal Initiative

Fourth BIMSTEC Summit kicks off

    Kathmandu, Aug 30: The Fourth Summit of Bay of Bengal Initiative for Multi-Sectoral